Repair works on the Hack Bridge in Novoli have begun.

The tram viaduct was seriously damaged by a fire on the night of December 30, 2025.

The bridge‑lifting operations will take place in two phases during the nights of January 28 and 29, 2026, from 10:00 p.m. to 4:00 a.m. Therefore, from 10:00 p.m. until the end of service on January 28, and from 10:00 p.m. until the end of service on January 29, Line T2 will operate with a reduced service: from Peretola Airport to Regione and back, and from Redi to San Marco Università and back.

Replacement bus services will be active between the stops Regione and Redi in both directions.

The bike lane adjacent to the viaduct will remain closed until the end of the works. Monitoring stations are active to detect any abnormal movements in the bridge structure.

In case of adverse weather conditions, postponing the intervention may be considered.